A simple project listing of five activities, their predecessors and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None 3 B A 2 C A 1 D B and C 3 E D 4 Using the Single Time Estimate CPM procedure, what is the Latest Finish Time for the last activity in this project (i.e., the total time to complete the project)?