Actual labor rate $16 per hour Actual materials price $160 per ton Standard labor rate $15.50 per hour Standard materials price $163 per ton Quantities Actual hours incurred and used 5,000 hours Actual quantity of materials purchased and used 1,700 tons Standard hours used 5,040 hours Standard quantity of materials used 1,675 tons (a) Compute the total, price, and quantity variances for materials and labor. Total materials variance $enter a dollar amount select an option Materials price variance $enter a dollar amount select an option Materials quantity variance $enter a dollar amount select an option Total labor variance $enter a dollar amount select an option Labor price variance $enter a dollar amount select an option Labor quantity variance
Solved
Show answers
More tips
- H Health and Medicine Mercury Thermometer Danger: What to do when a thermometer breaks?...
- F Food and Cooking How to cook crayfish? Everything you need to know...
- G Goods and services LED-подсветка в LCD-телевизорах: 5 причин, почему она лучше других технологий...
- P Photography and Videography Understanding HDR: How It Works and Why You Need It...
- G Goods and services Which TV is better - LCD or Plasma?...
- S Sport How to Learn to Pull Up on Monkey Bars?...
- L Leisure and Entertainment Scrapbooking: What is it and Why is it Becoming More Popular?...
- C Computers and Internet Where did torrents.ru move to?...
- B Business and Finance Understanding Cash Flow: What It Is and How It Works...
Answers on questions: Business
- M Mathematics the temperature at 3:00 pm was -20 degrees. the temperature increased by 25 degrees by 8:00pm. Write an equation to represent the new temperature...
- M Mathematics What is the measurement of R ?...
- G Geography Please help guys I really need it. Match the letter with the name of the place it represents on the map. Chile Andes Mountains Amazon Basin Atacama Desert Brazil Peru...
- C Chemistry 12. When the same quantity of electricity was passed through a dilute solution of sodium hydroxide and through a molten solution of lead bromide, 0.100 mol of lead was...
- P Physics Estrogen speeds up the heart rate. True False...
Ответ:
Materials price variance $5,100 F
Materials quantity variance $4,075 U
Total labor variance $2,500 U
Labor price variance $620 F
Explanation:
a) Data and Calculations:
Actual Standard
Labor rate per hour $16 $15.50
Material price per ton $160 $163
Labor hours 5,000 5,040
Materials 1,700 1,675
a) Total price variance for materials = Standard price per ton - Actual price per ton * Actual materials
= $163 - $160 * 1,700
= $5,100 F
b) Total quantity variance for materials = Standard quantity - Actual quantity * Standard price
= 1,675 - 1,700 * $163
= 25 * $163
= $4,075 U
c) Total price variance for labor = Standard rate per hour - Actual rate per hour * Actual labor hours
= $15.50 - $16 * 5,000
= -$0.50 * 5,000
= $2,500 U
d) Total quantity variance for labor = Standard labor hours - Actual labor hours * Standard rate
= 5,040 - 5,000 * $15.50
= $620 F