Amachine is available 10 hours a day. each part takes 90 minutes to fabricate and 10 minutes to setup. 10% of the parts made are defective and must go through the machine again to be reworked, during which both setup and fabrication have to be performed again. the machine is idle for any unused time. on average, 5 good parts are made each day. what is the overall equipment effectiveness of the machine?