An analyst, having solved a linear programming problem, determined that he had 10 more units of resource q than previously believed. upon modifying his program, he observed that the optimal solution did not change, but the value of the objective function increased by $30. this means that resource's q's shadow price was: a.$1.50.b.$3.00.c.$6.00.d.$15.00e.$30.00.