Jamison Construction has implemented a cost estimation system using regression analysis. The variable cost per hour of labor is $35 and the fixed cost was determined to be $186,000. If Jamison projects it will be working 204,000 hours in 2019, what is the projected total cost
Solved
Show answers
More tips
- H Health and Medicine How to Get Rid of Dandruff?...
- S Sport How to Choose Tennis Rackets?...
- H Health and Medicine AKDS Vaccination: Ensure Your Child s Safety...
- H Health and Medicine Naskol ko Opasen Ukus Kleshcha i Kak Ego Raspoznat...
- C Computers and Internet How to Delete Your Account on Odnoklassniki...
- H Health and Medicine What to Do When Your Jaw Locks Up?...
- G Goods and services What Are the Most Popular Services?...
- P Philosophy How did the concept of module arise in computer science?...
Answers on questions: Business
- B Business Question 1 of 10 Amanda s bank offers a savings account with a 2.8% APR, compounded monthly. What is the actual annual percentage yield on this account? O A. 2.84% B. 2.85% O C....
- H History Why did many americans criticize the mexican war? how did they see expansion as a threat to american liberties?...
- A Arts The ides of march is on a) 01-mar b) 13-mar c) 15-mar d) 31-mar plz !...
- B Biology Most mutations that cause cancer occur within body cells, and body cell mutations are not inherited. if cancer is not inherited, why does cancer statically appear to run in families?...
- H History What was one result of the expanding railroad system...
- M Mathematics During his 2007 mvp season for the new york yankees, alex rodriguez hit 98 singles, 31 doubles, 0 triples, and 54 home runs in a total of 583 at bats. the following table arranges...
- H History What social issues caused civil unrest in america in the last half of the 20th century...
- M Mathematics The area of a rectangular patio is 5 6/8 square yards and its length is 1 1/2 yards. what ia the patios width in yards...
- M Mathematics 16 more than eight of a certain number is twenty four more than 6 times of thatnumber....
- P Physics Amoving object is in equilibrium. which best describes the motion of the object if no forces change?...
Ответ:
$7,326,000
Explanation:
Calculation for what is the projected total cost
Using this formula
Projected total cost=(Projected hours*Variable cost per hour of labor)+Fixed cost
Let plug in the formula
Projected total cost=(204,000 hours*$35)+$186,000
Projected total cost=$7,140,000+$186,000
Projected total cost=$7,326,000
Therefore the projected total cost will be $7,326,000
Ответ:
A
Explanation: