On February 1, 2020, Nash's Contractors agreed to construct a building at a contract price of $5,700,000. Nash's estimated total construction costs would be $3,920,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:
2020 2021 2022
Total costs incurred to date $1,470,000 $2,580,000 $4,550,000
Estimated costs to complete 2,450,000 1,720,000 -0-
Customer billings to date 2,100,000 3,920,000 5,500,000
Collections to date 1,900,000 3,400,000 5,400,000
Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2020, 2021, and 2022.
2020 $ 2020 $
2021 $ 2021 $
2022 $ 2022 $
Solved
Show answers
More tips
- H Health and Medicine 10 Simple and Effective Tips on How to Lose Weight in a Week...
- C Computers and Internet Where did torrents.ru move to?...
- B Business and Finance Understanding Cash Flow: What It Is and How It Works...
- C Computers and Internet What Are Peers and Seeds in Torrenting?...
- H Health and Medicine 10 Simple Techniques on How to Boost Your Mood...
- G Goods and services How to Choose the Right High Chair for Your Baby?...
- S Style and Beauty Learn how to tie a keffiyeh on your head like a pro...
- S Style and Beauty How to braid friendship bracelets?...
Answers on questions: Business
- B Business 1. As a young child, Karina had a passion for animals and environmental issues. After she graduated from college, Karina landed a job in an organization whose mission is...
- B Business What is a common product that would be affected by a market economy?...
- B Business An accounting professor is considering opening his own consulting firm. To do so, she will have to quit her current job, that pays $125,000 a year, and take over a building...
- B Business I need help plz rat*e me...
- M Mathematics Spencer plants a 7-inch tomato plant in his garden. The plant grows by about 15% per week for several months. Which formula represents the height h of the tomato plant (in...
- M Mathematics What is 10 times as much as 0.7....
- M Mathematics A highway whose primary directions are north-south is being constructed along the coast. Near a city, a bay obstructs the straight path of the road. Since the cost of a bridge...
- B Biology What is the main function of the Krebs cycle? A. Breaking down energy carriers B. Using pyruvate to make energy carriers C. Producing oxygen for use in photosynthesis D....
- M Mathematics Un auto usado es ofrecido con el 20%de descuento con respecto a uno nuevosi la suma descontada es de 8000 cualesson los costo delos dos vehículos...
- B Business Which is true about your retirement savings? It will lower the amount of financial aid your child may receive. It should be put off until you re sure you have enough money...
Ответ:
Nash's Contractor
Gross profit that should be recorded for 2020, 2021, and 2022:
Percentage -of completion Completed-contract
2020 $___667,500 2020 $___0
2021 $361,395 2021 $0
2022 $121,105 2022 $1,150,000
Explanation:
a) Data and Calculations:
Contract price = $5,700,000
Estimated construction costs = $3,920,000
Project completion date = 2022
Costs and Billings:
2020 2021 2022
Total costs incurred to date $1,470,000 $2,580,000 $4,550,000
Estimated costs to complete 2,450,000 1,720,000 -0-
Customer billings to date 2,100,000 3,920,000 5,500,000
Collections to date 1,900,000 3,400,000 5,400,000
Percentage of completion:
2020:
Revenue = $2,137,500 ($1,470,000/$3,920,000 * $5,700,000)
Cost incurred = 1,470,000
Gross profit = $667,500
2021:
Revenue = $1,471,395 ($1,110,000/$4,300,000 * $5,700,000)
Cost incurred = 1,110,000
Gross profit = $361,395
2022:
Revenue = $2,091,105 ($5,700,000 - $2,137,500 - $1,471,395)
Cost incurred 1,970,000
Gross profit = $121,105
Completed contract
2022: Revenue = $5,700,000
Total costs = 4,550,000
Gross profit = $1,150,000