On February 1, 2020, Nash's Contractors agreed to construct a building at a contract price of $5,700,000. Nash's estimated total construction costs would be $3,920,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022
Total costs incurred to date $1,470,000 $2,580,000 $4,550,000
Estimated costs to complete 2,450,000 1,720,000 -0-
Customer billings to date 2,100,000 3,920,000 5,500,000
Collections to date 1,900,000 3,400,000 5,400,000

Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2020, 2021, and 2022.

2020 $ 2020 $
2021 $ 2021 $
2022 $ 2022 $