quence: Four jobs, A, B, C, and D have to be done on four machines, M1, M2, M3, and M4 in the operation sequence as given below. Draw Gantt charts showing the scheduling of these jobs based on: (a) Shortest Processing Time. (b) Least Slack. Determine average time per job, number of jobs late, and maximum lateness. Jobs Operations Due Date 1 2 3 4 machines -- hours A M1 - 2 M3 - 4 M2 - 3 M4 - 6 18 B M1 - 4 M2 - 3 M3 - 4 12 C M2 - 4 M3 - 5 M4 - 3 16 D M4 - 2 M1 - 3 M3 - 5 14 M1 M2 M3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 Shortest Pro