Suppose a project plan had three distinct paths through the network: The first path consisted of activities A (duration 3 days), B (duration 4 days), and C (duration 5 days). The second path consisted of activities D (duration 4 days), E (duration 5 days), and F (duration 5 days). The third path consisted of activities G ( duration 2 days), H (duration 3 days), and I (duration 8 days). Which is the critical path