The shop works two shifts per​ day, 8 hours per​ shift, 220 days per year.​ Currently, the company operates four​ machines, and desires a 25 percent capacity cushion. How many machines should be purchased to meet the upcoming​ year's demand without resorting to any​ short-term capacity​ solutions?