Which of these statements regarding project crashing is true?
crashing is not possible unless there are multiple critical paths.
activities not on the critical path cannot become critical after crashing.
crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
crashing a project often reduces the time it takes for lengthy or complex, but noncritical activities.
Solved
Show answers
More tips
- O Other Discovering the Funniest Joke Ever Told...
- F Food and Cooking How to Make Napoleon Cake: A Step-by-Step Guide...
- F Food and Cooking From Latte to Espresso: Which Coffee Drink is the Most Popular on Earth?...
- C Computers and Internet How to Set Up Internet on iPhone? Detailed Guide with Step-by-Step Instructions...
- F Family and Home How to Teach Your Child to Speak: Tips and Recommendations...
- P Philosophy Agnosticism: Opinion or Belief?...
- S Style and Beauty How to choose the best mascara for your eyelashes...
- F Food and Cooking Discover Delicious Recipes You Can Make with Ground Meat...
- C Computers and Internet Google Search Tips and Tricks: Everything You Need to Know...
- S Science and Technology Why is there no gravity on other planets?...
Answers on questions: Business
- M Mathematics A flying disc has a 5 ⅖ inch radius. What is its approximate circumference, rounded to the nearest inch?...
- C Chemistry Astudent was given a 0.15 m solution of an unknown diprotic acid h2a and asked to determine the ka1 and ka2 values for the diprotic acid. the student titrated 46 ml of the 0.15...
- H History Which sentence in this excerpt from the open boat by stephen crane uses personification? 333333333...
- E English In a standard dictionary, where can you find the key to pronunciation marks?...
Ответ:
The correct answer is letter "A": Crashing is not possible unless there are multiple critical paths.
Explanation:
Project crashing is a technique used to reduce the duration of a project to the least amount of extra cost by decreasing one or more critical activities. All of this is usually arranged in multiple entry charts where each critical activity receives the name of "critical path". It is imperative to have several critical paths so the crashing can be the most effective possible.
Ответ:
$4,900
Explanation:
Calculation to determine What amount of interest revenue from the lease should Crane report in its 2021 income statement
Interest revenue=8%/2*($144000 - $21500)
interest revenue=4%*$122,500
interest revenue = $4,900.
Therefore the amount of interest revenue from the lease should Crane report in its 2021 income statement is $4,900