You are working with your integrated project team to sequence activities on the aircraft modification project you are leading. You are looking for the factors, constraints, and potential dependencies among project activities that can influence the way activities are sequenced, as well as help you understand the relationship between activities and the need for leads and lags. Where could you find this information? A. Project schedule.
B. Assumption log.
C. Basis of estimates.
D. Work breakdown structure.