During the design of a product for a customer, your design team finds that an electrical component is
not working as planned. This design flaw will add three days to the specified completion date.
Which choice demonstrates following through on the commitment you made to the customer?
You do nothing. It is normal that projects are often extended beyond the deadline
You and your team create and submit a plan to your supervisor that will require overtime but solve the issue.
You inform your supervisor about the person on the team who made the design flaw and recommend having that person fix the
problem
You work hard to make up the lost time by finding a couple of minor steps to skip. You and your peers do not want to upset your
boss with this information