![lilyrockstarmag](/avatars/14445.jpg)
lilyrockstarmag
21.07.2020 •
Mathematics
35 workers are employed to complete the construction in 16 days. Before the work starts, he is told to complete the task in 14 days. Assuming that all the workers work at the same rate, how many more workers does he need to employ in order to complete the project.
Solved
Show answers
More tips
- F Family and Home How to Choose a Baby Stroller: Tips from Experienced Parents...
- H Health and Medicine 5 Simple Steps to Quit Smoking for Good...
- C Computers and Internet How to Download Videos from YouTube? Simple Steps to Download Any Content...
- H Health and Medicine What is the Normal Blood Sugar Level in a Healthy Person?...
- S Style and Beauty How to Get Rid of Acne: Scientifically Proven Methods...
- L Leisure and Entertainment How to Choose the Perfect Gift for Men on February 23rd?...
- C Computers and Internet How to Delete Your Account on Odnoklassniki...
- H Health and Medicine 10 Simple and Effective Tips on How to Lose Weight in a Week...
- F Food and Cooking What s the Best Rice for Cooking Plov?...
- F Family and Home How to Get Rid of Your Neighbors?...
Answers on questions: Mathematics
- M Mathematics 8 more than the quotient of a number and 2 is 14. find the number...
- M Mathematics What is the magnitude of vector 5, -3...
- M Mathematics To solve 2x=8 you need to divide by what number? PLEAS HELP...
- B Biology Which of these describes one of the functions of the nervous system? O A. removing waste materials from the body OB. sensing changes in the external environment c. transporting...
- M Mathematics Annapolis Company completes job #601 which has a standard of 540 labor hours at a standard rate of $18.20 per hour. The job was completed in 500 hours and the average actual...
- H History Which language were the natives forced to learn at school...
Ответ:
40 workers
Step-by-step explanation:
This job requires 35 workers and 16 days, so it requires
35 * 16 = 560 worker-days to complete
If you only have 14 days, then you need
560 worker-days/14 days = 40 workers
Ответ: