A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less?
Solved
Show answers
More tips
- H Health and Medicine How to Whiten Teeth and Get the Perfect Smile...
- S Style and Beauty How to Properly Apply Eye Makeup: Tips from a Professional Makeup Artist...
- A Auto and Moto How Can Parking Sensors Help Drivers?...
- C Computers and Internet Make Money Online: Secrets and Essential Ways...
- A Auto and Moto What is the Average Lifespan of an Engine in a Car?...
- H Health and Medicine What You Need to Know About Nasal Congestion in Infants: Causes, Symptoms, and Treatment...
- S Science and Technology Discovering the Anatomy of an LCD TV Screen...
- F Food and Cooking How to Get Reconfirmation of Registration?...
- F Food and Cooking Why Doesn t the Confirmation Link Come to Email?...
- F Food and Cooking Deflope: What is it and how does it work?...
Answers on questions: Mathematics
- M Mathematics Solve the equation using mental math x-1/5 = 4 2/5...
- M Mathematics Convert y = 7x2 - 56x - 21 to vertex form by completing the square. Choose the correct equation....
- M Mathematics Nancy buys 2 large pizzas for her brother s birthday party. The girls at the party eat 78 of a large pizza. The boys at the party eat 58 of a large pizza. Nancy says about 112 pizzas...
- M Mathematics The diameter of a circle measures 32 mm. What is the circumference of the circle? Use 3.14 for , and do not round your answer. Be sure to include the correct unit in your answer....
- M Mathematics Harharhaehr4ut5ihkfjharharhaehr4ut5ihkfjharharhaehr4ut5ihkfjharharhaehr4ut5ihkfj...
- M Mathematics Which situation can be represented by -48/3 A. Jose’s team lost a football game by 12 points 3 times this season. B. Franklin withdrew $48 from his savings account in 3 equal withdrawals....
- M Mathematics What is the range of this relation...
- M Mathematics Please help me. I need a step by step explanation....
- M Mathematics If there is not an isolated variable, how do you use substitution? Explain your steps....
- M Mathematics Find the product. -3( -12) -3( -12) =...
Ответ:
the probability that the project will be completed in 95 days or less, P(x ≤ 95) = 0.023
Step-by-step explanation:
This is a normal probability distribution question.
We'll need to standardize the 95 days to solve this.
The standardized score is the value minus the mean then divided by the standard deviation.
z = (x - xbar)/σ
x = 95 days
xbar = mean = 105 days
σ = standard deviation = √(variance) = √25 = 5
z = (95 - 105)/5 = - 2
To determine the probability that the project will be completed in 95 days or less, P(x ≤ 95) = P(z ≤ (-2))
We'll use data from the normal probability table for these probabilities
P(x ≤ 95) = P(z ≤ (-2)) = 0.02275 = 0.023
Ответ:
At the end of 6 years Jin pays the amount $ 20,160 in total.
Step-by-step explanation:
The Principal Value(P) = $18,000
Time(T) = 6 years
Rate of Interest(R) = 2%
Simple Interest =![\frac{P \times R \times T}{100}](/tpl/images/0342/1537/f1a30.png)
So, SI =![\frac{18,000 \times 2 \times 6}{100}](/tpl/images/0342/1537/a172a.png)
= $2,160
So, the interest amount = $2,160
Now, total amount to be paid = Principal Value + Interest Value
Amount = $18,000 + $2,160 = $ 20,160
Hence, at the end of 6 years Jin pays $ 20,160.