Amasonry contractor is preparing an estimate for building a stone wall and gate. he estimates that the job will take a 40-hour work week. he plans to have two laborers at $10 per hour and six masons at $21 per hour. he'll need $3337 worth of materials and wishes to make a profit of $400. write a mathematical statement that will give the estimated cost of the job. then calculate this total.
Solved
Show answers
More tips
- A Auto and Moto Mastering One-Movement Parking: All You Need to Know...
- P Photography and Videography Understanding HDR: How It Works and Why You Need It...
- P Photography and Videography How to Choose the Perfect Photo Paper for Your Images?...
- C Computers and Internet How to Choose an Uninterruptible Power Supply (UPS) for Your Computer: Expert Tips...
- S Science and Technology How to choose a home theater system?...
- A Auto and Moto How to Choose a Car Wash? Tips and Recommendations...
- A Animals and plants How ants survive winter: exploring the secrets of their winter life...
- C Construction and repair How to Choose the Best Underfloor Heating?...
- S Sport When is the Champions League final?...
- S Sport When and Where Will the 2014 World Cup be Held?...
Answers on questions: Mathematics
- M Mathematics Linda s account has a balance of −$45.50. if she owes the bank more than $30, her account gets closed. which of the following is true about linda s account?...
- M Mathematics Can you me with this? i don t seem to understand.....
- M Mathematics The results of a school election are shown in the circle graph below. (kwab 15%, chris 30%, angelina 25%, jonathan 30%). there were 2,500 votes cast in all. how many votes did angelina...
- H Health Amutation may be thought of as a misprint or mistake in the dna. true false...
- C Computers and Technology Assume that instead of having only a single processor, you have 100. Design a parallel algorithm that utilizes these additional resources to speed up the solution to the previous...
- B Biology Compare the two theories regarding the extinction of dinosaurs. They have all BUT ONE point in common. That is...
- C Chemistry An elements atomic number is 47. how many protons would an atom of this element have? protons...
Ответ:
$9,577
Step-by-step explanation:
Given:
Estimated time for the job = 40 hours
Number of laborers = 2
Per hour laborers cost = $10
Number of masons = 6
Per hour mason cost = $21
Worth of material = $3337
Estimated Profit = $400
Now,
The total amount spent on laborers
= Number of laborers × total working hours × Cost per hour
= 2 × 40 × $10
= $800
The total amount spent on masons
= Number of masons × total working hours × Cost per hour
= 6 × 40 × $21
= $5040
Hence,
the total estimated cost for the job
The total amount spent on laborers $800
The total amount spent on masons $5,040
Worth of material $3,337
Estimated Profit $400
Total estimated cost $9,577