roseemariehunter12
07.06.2021 •
Mathematics
If 80 persons can perform a piece of work in 16 days of 10 hours each, how
many men will perform a piece of work twice as great in tenth part of the time
working 8 hours a day supposing that three of the second set can do as much
work as four of the first set?
Solved
Show answers
More tips
- S Society and Politics Is It Fact or Fiction? Let s Talk About Anton Chekhov s Pseudonym...
- S Sport Playing Bowling: Rules and Advice for Novices...
- C Computers and Internet How to Properly Repartition a Hard Drive?...
- A Auto and Moto What Is the Cost of Customs Clearance for a Car in Russia?...
- L Leisure and Entertainment Should You Buy a Ceramic Knife?...
- C Computers and Internet How to easily and quickly disable Firebug in Gmail and Google Docs...
- G Goods and services How to sew a ribbon: Tips for beginners...
- F Food and Cooking How to Make Mayonnaise at Home? Secrets of Homemade Mayonnaise...
- C Computers and Internet Which Phone is Best for Internet Surfing?...
- F Food and Cooking Everything You Need to Know About Pasta...
Answers on questions: Mathematics
- M Mathematics Which points are reflections across the x-axis? Which points are reflections across the y-axis? Justify your answer....
- M Mathematics Aglacier advanced down a mountain from an elevation of 2010 m to 1780 m in 5 years. what was the glaciers rate of change...
- S Social Studies Which of the following ensured the right of citizenship for all races? a) the fourteenth amendment b) the bill of rights c) the loving v. virginia decision d) the...
- M Mathematics Select the correct answer. When graphed, the three lines y = -x + 2, y = 2x − 1, and y = x − 2 intersect in such a way that they form a triangle. What are the coordinates...
- H History I need the chart for John adams please help...
Ответ:
The number of men needed to perform a piece of work twice as great in tenth part of the time working 8 hours a day supposing that three of the second set can do as much work as four of the first set is:
1200 men.Step-by-step explanation:
To find the answer, first, we're gonna find how many hours take to make the piece of work in 16 days, taking into account each day just has 10 hours:
Number of hours to make a piece of work = 16 * 10 hoursNumber of hours to make a piece of work = 160 hours.Now, we divide the total hours among the number of persons:
Equivalence of hours per person = 160 hours / 80 persons.Equivalence of hours per person = 2 hours /personThis equivalence isn't the real work of each person, we only need this value to make the next calculations. Now, we have a piece of work twice as great as the first, then, we can calculate the hours the piece of work needs to perform it (twice!):
Number of hours to make the second piece of work = 160 hours * 2Number of hours to make the second piece of work = 320 hoursWe need to make this work in tenth part of the time working 8 hours a day, it means:
Time used to the second work = 320 hours / 10Time used to the second work = 32 hours Time used to the second work = 32 hours / 8 hours (as each day has 8 hours)Time used to the second work = 4 daysNow, we know three of the second set can do as much work as four of the first set, taking into account the calculated equivalence, we have:
Work of four workers of first set = Work of three workers of second setWork of four workers of first set = Equivalence * 4 persons.Work of four workers of first set = 2 hours /person * 4 personsWork of four workers of first set = 8 hours.So, three persons of the second set can make a equivalence of 8 hours. At last, we calculate all the number of workers we need in a regular time:
Number of needed workers in a regular time = (320 hours / 8 hours) * 3 persons.Number of needed workers in a regular time = 40 * 3 personsNumber of needed workers in a regular time = 120 personsRemember we need to perform the job not in a regular time, we need to perform it in tenth part of the time, by this reason, we need 10 times the number of people:
Number of needed workers in tenth part of the time = 120 persons * 10Number of needed workers in tenth part of the time = 1200 personsWith this calculations, you can find the number of men needed to perform a piece of work twice as great in tenth part of the time working 8 hours a day supposing that three of the second set can do as much work as four of the first set is 1200 persons.