Quality control. As part of a quality control process for computer chips, an engineer at a factory randomly samples 212 chips during a week of production to test the current rate of chips with severe defects. She finds that 27 of the chips are defective.
(a) What population is under consideration in the data set?
(b) What parameter is being estimated?
(c) What is the point estimate for the parameter?
(d) What is the name of the statistic can we use to measure the uncertainty of the point estimate?
(e) Compute the value from part (d) for this context.
(f) The historical rate of defects is 10%. Should the engineer be surprised by the observed rate of defects
during the current week?
(g) Suppose the true population value was found to be 10%. If we use this proportion to recompute the value in part (e) using p = 0.1 instead of pˆ, does the resulting value change much?
Solved
Show answers
More tips
- P Philosophy How to Properly Create a Vision Board?...
- C Computers and Internet What is Web 2.0 and How Does it Work?...
- S Style and Beauty Is Photoepilation the Solution to Unwanted Hair Forever?...
- O Other What is a Disk Emulsifier and How Does it Work?...
- F Family and Home What does a newborn need?...
- F Family and Home Choosing the Right Car Seat for Your Child: Tips and Recommendations...
- F Food and Cooking How to Get Reconfirmation of Registration?...
- C Computers and Internet How to Get Rid of Spam in ICQ?...
- A Art and Culture Who Said The Less We Love a Woman, the More She Likes Us ?...
- F Family and Home How to Get Rid of Your Neighbors?...
Answers on questions: Mathematics
- M Mathematics a sine function has the following key features: frequency = 18π amplitude = 6 midline: y = 3 y-intercept: (0,3) the function is not a reflection of its parent function over...
- M Mathematics Find the probability of at least 2 girls in births. assume that male and female births are equally likely and that the births are independent events. round to three decimal...
- M Mathematics Atotal of 613 tickets were sold for the school play they were either adult tickets or student tickets. there were 63 more student tickets sold than adult tickets. how many...
- M Mathematics Luca shows his work in finding the solution to 2−6x=5−5(x−1) . after checking his answer in the original equation, he found that it did not work. where did he make a mistake?...
- M Mathematics What is the value of x? enter your answer as a decimal....
- M Mathematics Wo people, a and b, agree to play a series of fair games until one person has won five games. they each have wagered the same amount of money, the intention being that the...
- M Mathematics This prism has a volume of 112 cm3. what would the volume of the prism be if each dimension was doubled? (scale factor is 2) 224 cm3 896 cm3 448 cm3 336 cm3...
- M Mathematics Aboat traveled downstream a distance of 68 mi and then came right back. if the speed of the current was 5 mph and the total trip took 5 hours and 40 minutes, find the average...
- M Mathematics Aprime is a number that has exactly factors...
- M Mathematics Jacob and isaac decided to run to the basketball court after school. the basketball court is 514 miles from school. the boys run at a pace of 338 miles per hour. enter the...
Ответ:
See Explanation
Step-by-step explanation:
According to the Question,
Given That, As part of a quality control process for computer chips, an engineer at a factory randomly samples 212 chips during a week of production to test the current rate of chips with severe defects. She finds that 27 of the chips are defective.(a) The sample is from all computer chips manufactured at the factory during the week of production. We might be tempted to generalize the population to represent all weeks, but we should exercise caution here since the rate of defects may change over time.
(b) The fraction of computer chips manufactured at the factory during the week of production that had defects.
(c) Estimate the parameter using the data: phat = 27/212 = 0.127.
(d) Standard error (or SE).
(e) Compute the SE using phat = 0.127 in place of p:
SE ≈ √(phat(1−phat)/n) = 0.023.
(f) The standard error is the standard deviation of phat. A value of 0.10 would be about one standard error away from the observed value, which would not represent a very uncommon deviation. (Usually beyond about 2 standard errors is a good rule of thumb.) The engineer should not be surprised.
(g) Recomputed standard error using p = 0.1: SE = 0.021. This value isn't very different, which is typical when the standard error is computed using relatively similar proportions (and even sometimes when those proportions are quite different!).
Ответ: