The proprietor of midland construction company has to decide between two projects. he estimates that the first project will yield a profit of $170,000 with a probability of 0.7 or a profit of $130,000 with a probability of 0.3; the second project will yield a profit of $230,000 with a probability of 0.7 or a profit of$80,000 with a probability of 0.3.

find the expected profit for each project.

first project = ?
second project = ?