josephnievesr31
27.08.2019 •
Biology
Compare the four main layers of the atmosphere
Solved
Show answers
More tips
- F Food and Cooking How to Cook a Steak with Mustard Sauce? What Kind of Meat to Choose?...
- P Photography and Videography What is lens calibration and why is it needed?...
- F Family and Home Stay Warm but Don t Overheat: What is the Optimal Temperature for Your Home During Winter?...
- H Health and Medicine How to Treat the Flu: A Comprehensive Guide...
- O Other What is a Disk Emulsifier and How Does it Work?...
- F Family and Home What does a newborn need?...
- F Family and Home Choosing the Right Car Seat for Your Child: Tips and Recommendations...
- F Food and Cooking How to Get Reconfirmation of Registration?...
- C Computers and Internet How to Get Rid of Spam in ICQ?...
- A Art and Culture Who Said The Less We Love a Woman, the More She Likes Us ?...
Answers on questions: Biology
- B Biology Which vessels delivers lymph into the junction of the internal jugular vein and the subclavian vein?...
- M Mathematics 10 piont+brainlest why did the missionaries want to change native americans? they didn t like their clothing. they didn t like their food. they thought they were good hunters....
- B Business What is forms of buisness??...
- M Mathematics Which is in the hunders place 742.891...
Ответ:
Ответ:
A) cost variance = -10,000, schedule variance = -7,000, cost performance index = 0.853, schedule performance index = 0.892.
B) The project is behind schedule and it is over budget.
C) Estimate at completion = 181712 . worse than planned.
D) It will take 13.45 to finish this project.
Explanation:
a) Cost variance = EV - AC ==> 58000 - 68000 = -10000
Schedule variance = EV - PV ==> 58000 - 65000 = -7000
CPI = EV / AC ==> 58000 / 68000 = 0.853
SPI = EV / PV ==> 58000 / 65000 = 0.892
b) Since Scheduled Performance Index is less than 1, the project is behind schedule and if CPI is less than 1, the project is over budget .
c) EAC = BAC / CPI ==> 155000 / 0.853 = 181712
Project is expected to exceed budget , therefore it is performing worse than planned.
d) Expected time to complete 12/.892 = 13.45