sofipalis9869
sofipalis9869
29.03.2021 • 
Business

1. Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin: Activity Description Immediate Predecessor Time (Weeks) A Survey building site -- 6 B Develop initial design -- 8 C Obtain board approval A, B 12 D Select architect C 4 E Establish budget C 6 F Finalize design D, E 15 G Obtain financing E 12 H Hire contractor F, G 8 a. Draw a project network. b. Identify the critical path. c. Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans

Solved
Show answers

Ask an AI advisor a question