Andrew is the prom committee chairman. he is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. which project management process stage is andrew in?