Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time- 21 days Which of the following statements is TRUE about activity G?a. Activity G takes 14 days to complete. b. Activity G has a slack time of 8 days. c. Activity G is on the critical path. d. Activity G takes 2 days to complete.
Solved
Show answers
More tips
- A Art and Culture Attention, the Final Episode of Margo is Almost Here!...
- W Work and Career How to Start Your Own Business: Tips and Recommendations...
- S Society and Politics 10 Tips for Boosting Your Self-Esteem...
- C Computers and Internet How to Create a Folder on Your iPhone?...
- G Goods and services How to sew a ribbon: Tips for beginners...
- F Food and Cooking How to Make Mayonnaise at Home? Secrets of Homemade Mayonnaise...
- C Computers and Internet Which Phone is Best for Internet Surfing?...
- F Food and Cooking Everything You Need to Know About Pasta...
- C Computers and Internet How to Choose a Monitor?...
- H Horoscopes, Magic, Divination Where Did Tarot Cards Come From?...
Answers on questions: Business
- E English What does it mean to Psych yourself up? How does this term affect the meaning of the text...
- B Biology How do cigarettes and radiation cause cancer? View Available Hint(s) How do cigarettes and radiation cause cancer? by destroying healthy cells by repressing the...
- M Mathematics Maura runs 5 miles in 1.25 hours. Ava runs 3 miles in 50 minutes, or 0.83 hour. Who runs faster? Use the drop-down menu to show your answer. Choose Please help I...
- C Computers and Technology In an information system, the rules or guidelines for people to follow are called . A) procedures B) compiling C) database management D) data processing...
Ответ:
The correct answer is Activity G has s slack time of 8 days.