Assume that activity G has the following times: Early start time 7 days Early finish time 13 days Late start time 15 days Late finish time- 21 days Which of the following statements is TRUE about activity G?a. Activity G takes 14 days to complete. b. Activity G has a slack time of 8 days. c. Activity G is on the critical path. d. Activity G takes 2 days to complete.