Assume you are doing a cost benefit analysis. You are told that 1000 man-hours of labor are needed for the project, and that the wage is $20 / hour. Half the crew that would be hired are currently unemployed and receiving $10 / hour in unemployment benefits. The correct estimate of labor cost is... a. $20,000 b. $15,000 c. $10,000 d. can't tell with the information given