Christopher's Cranks uses a machine that can produce 120 cranks per hour. The firm operates 12 hours per dayfive days per week. Due to regularly scheduled preventive maintenance, the firm expects the machine to be running during approximately 90% of the available time. Based on experience with other products, the firm expects to achieve an efficiency level for the cranks of 85%. What is the expected weekly output of cranks for this company