CodeHead Software Inc. does software development. One important activity in software development is writing software code. The manager of the WordPro Development Team determined that the average software programmer could write 25 lines of code in an hour. The plan for the first week in May called for 4,650 lines of code to be written on the WordPro product. The WordPro Team has five programmers. Each programmer is hired from an employment firm that requires temporary employees to be hired for a minimum of a 40-hour week. Programmers are paid $32.00 per hour. The manager offered a bonus if the team could generate more lines for the week, without overtime. Due to a project emergency, the programmers wrote more code in the first week of May than planned. The actual amount of code written in the first week of May was 5,650 lines, without overtime. As a result, the bonus caused the average programmer's hourly rate to increase to $40.00 per hour during the first week in May. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. If an amount is zero, enter "0" and choose "Not applicable" from the dropdown.
Required:
a. If the team generated 4,650 lines of code according to the original plan, what would have been the labor time variance?
b. What was the actual labor time variance as a result of generating 5,650 lines of code?
c. What was the labor rate variance as a result of the bonus?
d. The manager is trying to determine if a better decision would have been to hire a temporary programmer to meet the higher programming demand in the first week of May, rather than paying out the bonus. If another employee was hired from the employment firm, what would have been the labor time variance in the first week?
Solved
Show answers
More tips
- S Style and Beauty Tricks and Tips: How to Get Rid of Freckles...
- H Health and Medicine What is Autism? Understanding the Basics of This Neurodevelopmental Disorder...
- F Food and Cooking The Most Delicious and Simple Fish in Batter Recipe...
- S Society and Politics 10 Tips for Boosting Your Self-Esteem...
- F Food and Cooking Which Calamari Salad is the Most Delicious?...
- H Health and Medicine Mercury Thermometer Danger: What to do when a thermometer breaks?...
- S Style and Beauty How to braid friendship bracelets?...
- F Food and Cooking Delight for Gourmets: How to Prepare Liver Pate...
- C Computers and Internet How to Learn to Type Fast?...
- H Health and Medicine Angina: Causes, Symptoms, and Treatment...
Answers on questions: Business
- S Social Studies The change to the direct election of Senators, the lowering of the voting age to 18 and the establishment of a two-term limit for Presidents are all examples of the...
- M Mathematics 712 : 74 is equal to 73 78 3 13...
- H History What were the philosophical underpinnings of the colonists’ revolts against the british?...
- A Arts What period are these ceramic figures from? what do historians know about these two ceramic figures? 1086-07-01-02-00_files/i0120000.jpg...
Ответ:
(a) Labor time variance = = $448Unfavourable
(b) Actual labor time variance = $832Favourable
(c) Labor rate variance = $1,600 Unfavourable
(d) Labor time variance if another employee was hired =$448Unfavourable
Explanation:
Given Data:
Standard quantity of output per hour per programmer = 25 lines
Standard rate per hour = $32
Budgeted output for first week in May = 4650 lines
Actual output= 5650 lines
Actual rate per hour = $40
Standard hours for 4650 lines(4650/25) = 186
Actual hours=5*40= 200
a. Calculating the labor time variance using the formula;
Labor time variance = Standard rate*(Actual hour-Standard hour) =$32*(200-186)
= $448Unfavourable
b. Calculating the actual labor time variance using the formula;
Labor time variance = Standard rate*(Actual time-Standard time)
But,
Standard time for 5650 lines = (5650/25) = 226 hours
Therefore,
Labor time variance = $32*(200-226)
= $832Favourable
c. Calculating the labor rate variance using the formula;
Labor rate variance = Actual hour*(Actual rate-Standard rate)
Labor rate variance = 200*(40-32)
= $1,600 Unfavourable
4. Calculating the labor time variance if another employee was hired , we have
Actual labor time=6*40= 240
Actual labor rate =$32
Labor time variance = Standard rate*(Actual hour -Standard hour) =$32*(240-226)
= $448Unfavourable
Ответ:
same
what you want to do
Explanation: