Consider a project that requires the completion of 7 tasks, as follows:
o Tasks A and B can begin simultaneously at the beginning ("time zero").
o Task C can only begin after task B is completed.
o Task D can only begin after task A is completed.
o Task E can only begin after task A is completed.
o Task F can only begin after task E is completed.
o Task G can only begin after tasks C and D are completed.
The expected durations (in days) of each task are as follows: A=15; B=15; C=10; D=10; E=30; F=20; G=40.
What is the expected completion of the whole project?
A. 50 days
B. 60 days
C. 70 days
D. 75 days
Consider the project from the previous question with the added complexity that the actual completion time of each task will be:
A) 15+ RANDBETWEEN(-8,8)
B) 20+ RANDBETWEEN(-8,8)
C) 10+ RANDBETWEEN(-8,8)
D) 10+ RANDBETWEEN(-8,8)
E) 30+ RANDBETWEEN(-8,8)
F) 20+ RANDBETWEEN(-8,8)
G) 40+ RANDBETWEEN(-8,8)
Using PERT, what is the expected completion time of the project?
A. 50 days
B. 60 days
C. 70 days
D. 75 days
Solved
Show answers
More tips
- A Art and Culture Attention, the Final Episode of Margo is Almost Here!...
- W Work and Career How to Start Your Own Business: Tips and Recommendations...
- S Society and Politics 10 Tips for Boosting Your Self-Esteem...
- C Computers and Internet How to Create a Folder on Your iPhone?...
- G Goods and services How to sew a ribbon: Tips for beginners...
- F Food and Cooking How to Make Mayonnaise at Home? Secrets of Homemade Mayonnaise...
- C Computers and Internet Which Phone is Best for Internet Surfing?...
- F Food and Cooking Everything You Need to Know About Pasta...
- C Computers and Internet How to Choose a Monitor?...
- H Horoscopes, Magic, Divination Where Did Tarot Cards Come From?...
Ответ:
D. 75 days
F) 20+ RANDBETWEEN (-8,8)
B. 60 days
Explanation:
The project has 7 tasks which needs to be completed to finish the project. There are task a and b which can start simultaneously so we will start these two tasks together to reduce the time of the total completion of project. The projects a and b can start at zero = 15 days
using the following equation we calculate days to complete the project.
15ab + 10cde + 20ge + 20fg = 75 days.
Ответ:
Operating cash flow $56,017.10
Explanation:
The computation of the operating cash flow is shown below:
Sales (8,500 × $55) $467,500
Less: Variable cost (8,500 × 28.62) -$243,270
Fixed costs -$170,000
Depreciation -$62,000
Income before tax -$7,770
Less: Tax -1,787.10
Net Income -$5,982.9
Add: Depreciation 62,000
Operating cash flow $56,017.10