Marlon's Pools, Inc., agrees to build a swimming pool for Robert, and starts the job. Unfortunately, Marlon's Pools fails to complete the construction of the pool. Robert hires California Pools, Inc., to finish the project. Robert may recover from Marlon's Pools

a. the contract price less costs of materials and labor.
b. the contract price.
c. the costs needed to complete construction.
d. profits plus the costs incurred up to the time of the breach