Nick Company has two products: A and B. The company uses activity-based costing. The estimated total cost and expected activity for each of the company's three activity cost pools are as follows:
Expected Activity
Activity Cost Pool Estimated Costs Product A Product B Total
Activity 1 $32,600 700 300 1,000Activity 2$17,600600 200 800Activity 3 $52,500 400100500
The activity rate under the activity-based costing system for Activity 3 is closest to:
Answer
a. $44.65
b. $105.00
c. $525.00
d. $205.00
Solved
Show answers
More tips
- S Style and Beauty How are artificial nails removed?...
- S Style and Beauty Secrets of Tying a Pareo: 5 Ways...
- F Food and Cooking 10 Reasons Why You Should Avoid Giving Re-Gifts: An Informative Guide...
- S Sport How to wrap boxing hand wraps? Everything you need to know!...
- A Animals and plants 5 Tips for Taking Care of Yews to Keep Them Green and Beautiful...
- H Health and Medicine How to Calm Your Nerves? Expert Tips That Actually Work...
- O Other What is a Disk Emulsifier and How Does it Work?...
- S Sport How to Pump Your Chest Muscle? Secrets of Training...
- C Computers and Internet How to Get Rid of 3pic Infector: Everything You Need to Know...
- S Style and Beauty How to Grow Hair Faster: Real Methods and Advice...
Answers on questions: Business
- E English Who knows what 3am is, my name mr cheese,....
- C Computers and Technology What is the keyboard shortcut to open the spelling and grammar dialog box in word?...
- M Mathematics The farm keeps 20 gallons of the milk produced each day to use on the farm and sells the rest of the milk to a distributor to be sold in stores. The farm packages...
- C Computers and Technology Write a function, swapsubtrees, that swaps all of the left and right subtrees of a binary tree. add this function to the class binarytreetype and create a program...
Ответ:
b. $105.00
Explanation:
The computation of the activity rate under the activity-based costing system is shown below:
For Activity 3,
The activity rate is
= Estimated cost ÷ Estimated activity
= $52,500 ÷ 500
= $105
We simply divided the estimated cost by the estimated activity to get the activity rate
All other information which is given is not considered. Hence, ignored it