Ortell Corporation is interested in cutting the amount of time between when a customer places an order and when the order is completed. Details for the first quarter of the year are provided here. Choose the correct answer from the options provided. Days Wait time 12 Inspection time 0.6 Process time 6 Move time 0.4 Queue time 8 Knowledge Check 01 What is the manufacturing cycle efficiency (MCE)