Project C will cost $30,000 and will generate $5,000 per year in new revenue. Project D will cost $120,000 and generate $50,000 per year in new revenue. Which is the better project from a payback period standpoint?
Solved
Show answers
More tips
- G Goods and services How to Make Soap at Home: Useful Tips for Beginners...
- C Computers and Internet How to Reinstall Windows: A Detailed Guide for Beginners...
- S Style and Beauty How to Get Rid of a Bruise: Tips and Tricks...
- F Food and Cooking Лечо: вкусное и простое блюдо для любой кухни...
- H Health and Medicine Relieving Swelling in Legs: Causes and Ways to Alleviate the Symptom...
Ответ:
Project D
Explanation:
Payback period calculates the amount of time it takes to recover the amount invested in a project.
Pay back period = Cost of project / revenue from project.
For project c, its Pay back period is $30,000 / $5,000 = 6 years
For project d, the Pay back period is $120,000 / $50,000 = 2.4 years
The project with the shorter Pay back period is better