Purple swift manufactures birdhouses in lots of 1010. each birdhouse takes 4545 minutes to paint. after 1010 birdhouses are painted, the company switches paint color which requires a one hourone hour changeover. assume that the company should changeover at the very beginning of the process. the company works 88 hours per shift, one shift per day, 215215 days per year. currently the company has one point booth. what is purple swift's paint capacity cushion if it builds 1 comma 8001,800 birdhouses per year?
Solved
Show answers
More tips
- A Art and Culture The History and Characteristics of Jazz Bands: A Deep Dive...
- W Work and Career Can Skill Alone Make You a Professional?...
- F Family and Home Daughter says: If you don t want to do it, don t do it. Should we persuade her?...
- S Science and Technology How to Secure Exam Sessions: Silence Mobile Phones in the Classroom...
- C Computers and Internet Which Phone is Best for Internet Surfing?...
- P Philosophy Is Everything We Strive for Eventually Achieved and Destroyed?...
- S Society and Politics Understanding Politics and Its Role in the Development of Civilization...
- P Philosophy Why Did God Create Man and Place Him in Obscurity?...
- S Society and Politics Skoptsy: Who They Are and How They Perform Castration?...
- O Other Childhood Fears: What Many of Us Experienced...
Answers on questions: Business
- B Business People who play a task-specialist role often:...
- M Mathematics In one baseball season, peter hit twice the difference of the number of home runs alice hit and 6. how many home runs did each player hit that season?...
- C Chemistry These two beakers represent solutions of hcl and naoh...
- H History Which american president is the most forgotten in history? (i need this for my research essay)...
- M Mathematics How to sketch the inequalities and how to shade them...
- A Arts Identify the step of the critical process that requires discussion of the material of which the work was made, and how it was created. a.) iconography b.) medium...
- M Mathematics How many subtraction signs should be placed between these digits to get the value of 23...
- M Mathematics Can someone explain the pattern? you. appreciate it...
- M Mathematics How do you find the volume of a cylinder...
- M Mathematics Two planes leave atlanta at 3 pm est. one flies east and travels at a speed of 75 kilo. per hour slower than the other plane witch is flying west. by 7 pm est the...
Ответ:
Utilization can be calculated using the formula utilization = average output rate / maximum capacity.
Utilization = number of lots x setup time + processing time x number of units / number of hours per day x working days per year
Utilization = [200 x 1 + (45/60) x 2000] / (8 x 215) = 1700 / 1720
Utilization = 0.9884
The utilization is 0.9884 or 98.84%. capacity cushion can be calculated by subtracting the utilization from 1. The capacity cushion is 0.01163 or 1.17%