Purple swift manufactures birdhouses in lots of 1010. each birdhouse takes 4545 minutes to paint. after 1010 birdhouses are painted, the company switches paint color which requires a one hourone hour changeover. assume that the company should changeover at the very beginning of the process. the company works 88 hours per shift, one shift per day, 215215 days per year. currently the company has one point booth. what is purple swift's paint capacity cushion if it builds 1 comma 8001,800 birdhouses per year?