repares in-flight meals for a number of major airlines. One of the company’s products is grilled salmon with new potatoes and mixed vegetables. During the most recent week, the company prepared 6,700 of these meals using 1,300 direct labor-hours. The company paid its direct labor workers a total of $16,900 for this work, or $13.00 per hour. According to the standard cost card for this meal, it should require 0.20 direct labor-hours at a cost of $12.50 per hour. Required: 1. What is the standard labor-hours allowed (SH) to prepare 6,700 meals? 2. What is the standard labor cost allowed (SH × SR) to prepare 6,700 meals? 3. What is the labor spending variance? 4. What is the labor rate variance and the labor efficiency variance?