Suppose you have a project with four tasks as follows: task 1 can start immediately and has a duration of 2. task 2 can start after task 1 is completed and has an estimated duration of 4. task 3 can start after task 2 has been completed and has an estimated duration of 5. task 4 can start after task 1 is completed and must be completed when task 3 is completed. its estimated duration is 8. what is the length of the critical path for this project? 9 10 11 12