The method used to collect information to use through all phases of the project life cycle is called
a. responsibility matrix
b. organization breakdown structure
c. work breakdown structure
d. priority matrix
e. work package
Solved
Show answers
More tips
- A Auto and Moto Battle for the Relocation of The Cherkizovsky Market: Who Won?...
- F Food and Cooking Homemade kvass: recipe and brewing process...
- O Other What is a Disk Emulsifier and How Does it Work?...
- H Health and Medicine How to Calm Your Nerves? Expert Tips That Actually Work...
- A Animals and plants 5 Tips for Taking Care of Yews to Keep Them Green and Beautiful...
- S Sport How to wrap boxing hand wraps? Everything you need to know!...
- F Food and Cooking 10 Reasons Why You Should Avoid Giving Re-Gifts: An Informative Guide...
- F Family and Home Tender Care for Your Parquet: Is it Possible to Clean Parquet?...
- S Style and Beauty How Are Eyelash Extensions Applied? All Your Questions Answered...
- F Food and Cooking 10 Tips for Proper Sushi Consumption...
Answers on questions: Business
- H History Write three sentences explaining why the Bill of Rights is necessary....
- M Mathematics Apicture has a width that is 17 inches shorter than the length, and its total area is 480 square inches. find the dimensions of the picture....
- B Business Identify the terms and coefficients -20+5p-7z...
- M Mathematics What is the equivalent expression of -1/7-5/16...
Ответ:
Letter C is correct. Work breakdown structure.
Explanation:
Work breakdown structure is a method used so that there is a necessary hierarchy so that the flow of project steps can be fulfilled more effectively. It is used to achieve project objectives and deliverables.
At each level of the Work Breakdown Structure Diagram there should be a schedule, time and estimated budget, so that the scope of the project can be better understood and integrated.
Ответ:
Explanation:
1. NPV = -1,700,000 + 2,055,000 * (1-0.008) / 1.02
= $298,588.24
2. Yes order should be fulfilled
3. Break-even probability = 1 - 1,700,000 * 1.02 /2,055,000
= 1 - 0.843795
15.62%