The predetermined overhead rate for zane production company is $10, comprised of avariable overhead rate of $6 and a fixed rate of $4. the amount of budgeted overheadcosts at normal capacity of $300,000 was divided by normal capacity of 30,000 directlabor hours, to arrive at the predetermined overhead rate of $10. actual overhead forjune was $19,000 variable and $12,100 fixed, and standard hours allowed for theproduct produced in june was 3,000 hours. the total overhead variance is