A project has a mean completion time of 54 weeks and a standard deviation of the project completion time of 2.95 weeks. What is the probability of completing the project within 52 weeks? Please put your answer in terms of a probability (i.e. a number between 0 and 1), and not a percentage.
Solved
Show answers
More tips
- C Computers and Internet Отправляем смс через интернет: легко и просто...
- L Leisure and Entertainment The Best Film of 2010: A Look Back at the Academy Awards...
- H Health and Medicine Simple and Effective: How to Get Rid of Cracked Heels...
- L Leisure and Entertainment What to Bring on a Hike? Essential Items to Pack for a Safe and Enjoyable Adventure...
- L Leisure and Entertainment Couchsurfing: A New Way to Travel...
- S Style and Beauty Autotanning: Harmful or Safe?...
- F Food and Cooking 10 Ideas for a Wedding Anniversary Gift...
- H Health and Medicine How to Reduce Sweating in the Heat and Beyond: Say Goodbye to Excessive Sweat...
- F Food and Cooking Do Aphrodisiacs Really Work? Separating Fact from Fiction...
- H Health and Medicine What to Eat to Lose Weight?...
Answers on questions: Mathematics
- M Mathematics Select ALL statements that accurately completes the statement below. A scale factor CAN NOT • Be less than one - Be greater than one o Be equal to zero Be equal to one...
- M Mathematics Phillipe buys 50 shares of green energy and 120 shares of tjh small-cap. what is phillipe’s total investment? a. $3,076.10 b. $3,112.10 c. $3,150.50 d. $3,186.50...
- M Mathematics Phillip created the net worth statement shown....
- M Mathematics If g(x)=2x-10 g(-1) is??...
- M Mathematics Find for me the answer of this law to indices36^y-1 ×6^2y-2=1...
Ответ:
0.2483
Step-by-step explanation:
Problems of normally distributed samples are solved using the z-score formula.
In a set with mean
and standard deviation
, the zscore of a measure X is given by:
The Z-score measures how many standard deviations the measure is from the mean. After finding the Z-score, we look at the z-score table and find the p-value associated with this z-score. This p-value is the probability that the value of the measure is smaller than X, that is, the percentile of X. Subtracting 1 by the pvalue, we get the probability that the value of the measure is greater than X.
In this problem, we have that:
What is the probability of completing the project within 52 weeks?
This is the pvalue of Z when X = 52.
So the answer is 0.2483
Ответ:
30%
Step-by-step explanation:
I did this on I-Ready