On March 9, Job ACC0002 was completed. The job cost sheet showed a total of $6,000 in direct materials and $8,000 in direct labour at a rate of $20 per direct labour hour. Manufacturing overhead is applied at $30 per direct labour hour. The debit to Finished Goods Inventory to record the completion of Job ACC0002 is