seby77L
05.05.2020 •
Mathematics
Problem 11-93 Waltner Corporation s management... Waltner Corporation's management reports that its average delivery cycle time is 25 days, its average throughput time is 7.7 days, its manufacturing cycle efficiency (MCE) is 0.43, its average move time is 0.3 day, and its average queue time is 3.00 days. Required: a. What is the wait time
Solved
Show answers
More tips
- F Family and Home How to Raise a Genius? Discover the Secrets Here...
- F Food and Cooking How to Properly Cook Buckwheat?...
- H Health and Medicine How to Tan in a Tanning Bed? Tips and Recommendations...
- S Style and Beauty How to Sew a Balloon Skirt: Detailed Tutorial and Tips on Choosing the Right Fabric...
- P Philosophy Personal attitude towards Confession: how to prepare and undergo the procedure correctly?...
- F Food and Cooking How to Make Cottage Cheese at Home: Simple and Quick Recipe with Step By Step Instructions...
- H Health and Medicine Which Water Are You Drinking? Is it Worth Buying Bottled Water?...
- H Health and Medicine What Makes a Man a Man?...
- H Health and Medicine What to Take with You to the Maternity Hospital?...
- F Food and Cooking What Foods Can Nursing Moms Eat?...
Answers on questions: Mathematics
- M Mathematics The quotient of s and three...
- M Mathematics Circumferance of a pizza with diameter of 10 inches...
- C Chemistry The loops in ptolemy’s heliocentric model , and those shown on the video , are called?...
- B Biology When a nurse uses information from other sources to rethink revise and apply knowledge to a clinical situation- information?...
- S Spanish Garcilaso de la Vega Garcilaso de la Vega (-1500-1536) fue un famoso poeta y escritor de España. El siguiente es uno de sus sonetos. Soneto XXIII En tanto que de rosa y azucena...
- M Mathematics Select the polynomial that is a perfect square trinomial. 36x2 − 4x + 16 16x2 − 8x + 36 25x2 + 9x + 4 4x2 + 20x + 25...
Ответ:
Complete question is;
Waltner Corporation's management reports that its average delivery cycle time is 25 days, its average throughput time is 7.7 days, its manufacturing cycle efficiency (MCE) is 0.43, its average move time is 0.3 day, and its average queue time is 3.00 days. Required: a. What is the wait time?
b. What is the process time?
c. What is the inspection time?
A) Wait time = 17.3 days
B) Process time = 3.311 days
C) Inspection time = 0.789 days
Step-by-step explanation:
A) we are given;
Delivery cycle time = 25 days
throughput time = 7.7 days
The formula for wait time is calculated from;
Delivery time = wait time + throughput time
So, wait time = Delivery time - throughput time
Wait time = 25 - 7.7 = 17.3 days
B) The process time is calculated from;
MCE = Process time/throughput time
So, process time = MCE x throughput time
We are given MCE = 0.43,thus, and we already know throughput time. Thus;
Process time = 0.43 x 7.7 = 3.311 days
C) The inspection time is gotten from;
throughput time = Process time + Inspection time + Move time + Queue time
Making inspection time the subject;
inspection time = throughput time - Process time - Move time - Queue time
Move time = 0.3 days
Queue time = 3 days.
Thus;
inspection time = 7.7 - 3.311 - 0.3 - 3.3 = 0.789 days