To complete a task in 15 days, a company has 4 people each working 8 hours a day. The company decide to have 5 people each working 6 hours a day. Assume that each person works at the same
rate.

a) How many days will it take the 5 people to complete the task?

b)Comment on how the assumption affects your answer to part (a).