What is the cumulative project budget for September in this time-phased budget? Activity July August September October November RFP 34,721Analysis 11,049 33,655 34,388 Design 33,718 34,474 26,759 36,328 Coding 7,713 34,905 40,244 Testing40,916 896 Training20,958 9,327 Roll-Out8,186 $152,927 $251,382 $155,330 $96,052