Mary reports that, on a productive week, she can develop the system requirements in four days, but during a normal week it should take around eight days. during the time frame that mary will be working on the requirements, things will be very hectic and this could cause the requirements to take as much as twelve days. what is the expected duration for gathering system requirements using three-point method
Solved
Show answers
More tips
- F Family and Home Parents or Environment: Who Has the Most Influence on a Child s Upbringing?...
- P Philosophy Unbelievable stories of encounters with otherworldly forces...
- L Leisure and Entertainment How to Choose the Perfect Gift for Men on February 23rd?...
- H Health and Medicine How to Treat Whooping Cough in Children?...
- H Health and Medicine Simple Ways to Lower Cholesterol in the Blood: Tips and Tricks...
- O Other How to Choose the Best Answer to Your Question on The Grand Question ?...
- L Leisure and Entertainment History of International Women s Day: When Did the Celebration of March 8th Begin?...
- S Style and Beauty Intimate Haircut: The Reasons, Popularity, and Risks...
- A Art and Culture When Will Eurovision 2011 Take Place?...
- S Style and Beauty How to Choose the Perfect Hair Straightener?...
Answers on questions: Business
- E English Heyyy free to talk im bo.red...
- C Chemistry I need help with number 15...
- S SAT Killiniq and Bergen are the same distance from the equator, and both cities are near the ocean. The information on the map tells you that the ocean surface temperature...
- P Physics My name is scooter hey fat boy you waa fight...
- A Arts What is my name hints first letter: m last letter: a only three letters wrong...
Ответ:
The expected duration for gathering system requirements using three-point method is 8 days.
We obtain the same answer when we use the Simple Average method and the PERT method.
We follow these steps while arriving at the answer.
We have the following information from the question:
Optimistic Value (O) - 4 days (best estimate of time taken to complete the task)
Most Likely Value (M) – 8 days (realistic estimate of time taken to complete the task)
Pessimistic Value (P) – 12 days (worst estimate of time taken to complete the task)
There are two formulas we can use to determine the expected duration by using the three-point estimation method.
Simple Average method: We use the following formula under this method.2. PERT method. The formula for this is:
Ответ:
engine assembler, survey reasearcher, auditor