Metal shelf company's standard cost for raw materials is $ 4.00 per pound and it is expected that each metal shelf uses two pounds of material. during october year 2, 25 comma 000 pounds of materials are purchased from a new supplier for $ 97 comma 000 and 13 comma 000 shelves are produced using 27 comma 000 pounds of materials. which statement is a possible explanation concerning the direct materials variances?
Solved
Show answers
More tips
- H Health and Medicine 10 Ways to Cleanse Your Colon and Improve Your Health...
- W Work and Career How to Write a Resume That Catches the Employer s Attention?...
- C Computers and Internet Е-head: How it Simplifies Life for Users?...
- F Family and Home How to Choose the Best Diapers for Your Baby?...
- F Family and Home Parquet or laminate, which is better?...
- L Leisure and Entertainment How to Properly Wind Fishing Line onto a Reel?...
- L Leisure and Entertainment How to Make a Paper Boat in Simple Steps...
- T Travel and tourism Maldives Adventures: What is the Best Season to Visit the Luxurious Beaches?...
- H Health and Medicine Kinesiology: What is it and How Does it Work?...
- O Other How to Choose the Best Answer to Your Question on The Grand Question ?...
Answers on questions: Business
- B Business Consider a simple economy whose only industry is fishing. In this industry, productivity—the amount of goods and services a worker can produce per hour—is measured by the number of...
- B Business SpyingEyes, Inc., a large data intelligence company, has storage technology at multiple sites that store redundant data from its servers at the main office. What risk management strategies...
- B Business Suppose there are three factories in Macroland and the following occurred in 2019: Metal, plastic and a car factory. Metal factory produces $200, plastic factory produces $500, and...
- B Business Jensen Company purchased a new machine on January 1, 2018, at a cost of $104,000. The company estimated that the machine has a salvage value of $8,000. The machine is expected to...
- B Business Compute the payback period for each of these two separate investments: a. A new operating system for an existing machine is expected to cost $290,000 and have a useful life of four...
- B Business Suppose Sam and Teresa are playing a game in which both must simultaneously choose the action Let Or Right. The payoff matrix that follows shows the payoff each person Will earn as...
- B Business Your company expects to receive CAD 1,200,000 in 90 days. The 90 day forward rate for CAD is $0.80 and the current spot rate is $0.75. If you use a forward hedge, estimate the cost...
- B Business Zero-coupon risk-free bonds are available with the following maturities and yield rates (effective, annual): Maturity(in years) Yield % 1 6 2 6.5 3 7 You need to buy corn for producing...
- B Business Wiley Hill opened Hill s Repairs, Inc. on March 1 of the current year. During March, the following transactions occurred and were recorded in the company s books: 1. Wiley invested...
- B Business Consider the markets for tap water, bottled water, cola, and beer. Assume there is only one provider of tap water, bottled water manufacturers use advertising to differentiate their...
Ответ:
There are 3 possible primary answers:
a. The production department had to use more materials since the quality of the material was inferior.The expectation that each metal shelf uses 2 lbs of materials is rounded off figure whereas in actual each metal shelf uses 2.0769 lbs of materialThere is a process loss of 0.0769 of material per metal shelf's manufacturing(3.7% process loss)Explanation:
Given:
Expected Material required per metal shelf = 2 lbs
Cost of raw material = 4 $/lb
Material purchased in Oct-year 2= 25,000 lbs
Cost of purchased material in Oct-year 2 = 97,000 $
Cost of material per lbs purchased in Oct-year 2 = 97000/25000 = 3.88 $/lb
Total shelves produced = 13,000 Nos
Total material used = 27,000 lbs
Actual material used per metal shelf = 27000/13000 = 2.0769 lbs/Nos
Thus it is concluded that either the expected materials' amount of 2 lbs was rounded off or there happened a process loss 0.0769 lbs per metal shelf.
Why not these?
Cost of material per lbs purchased in Oct-year 2 = 97000/25000 = 3.88 $/lb
b. The purchasing manager paid more than expected for materials
As the purchased lot was cheaper (@ 3.88 $/lb) than regular rate of 4$/lb therefore the purchase manager didn't pay more than expected.
c. Production workers were more efficient than anticipated
Actual material used per metal shelf = 27000/13000 = 2.0769 lbs/Nos
As the more material was used than expected thus this statement can't be true.
d. The overall materials variance is positive, no further analysis is necessary
Actual material used per metal shelf = 27000/13000 = 2.0769 lbs/Nos
Considering we are using more materials than expected so the overall material variance should not be positive and we should plan further analysis.
Ответ:
Direct material price variance
= (Standard price - Actual price) x Actual quantity purchased
=($4 - $3.38) x 25,000 pounds
= $3,000( F)
Direct material price variance is $3,000 favorable
Actual price = $97,000/25,000 pounds = $3.88
Direct material usage variance
= (Standard quantity - Actual quantity used) x Standard price
= (26,000 - 27,000) x $4
= $4,000(U)
Direct material usage variance is $4,000 unfavorable.
Standard quantity = 2 pounds x 13,000 shelves = 26,000 pounds
Explanation:
Direct material price variance is the difference between standard price and actual price multiplied by actual quantity purchased. Actual price is calculated as actual material cost divided by actual quantity purchased.
Direct material usage variance is the difference between standard quantity and actual quantity used multiplied by standard price. Standard quantity is the product of standard quantity per unit and actual unit produced.
Ответ:
sorry need koren po ng point kasi mag a ask lang din nmn po ako thnks po:(