Aworker performs a repetitive assembly task at a workbench to assemble products. each product consists of 25 components. various hand tools are used in the task. the standard time for the work cycle is 7.45 min, based on using a pfd allowance factor of 15%. if the worker completes 75 product units during an 8-hour shift, determine the number of standard hours accomplished.
Solved
Show answers
More tips
- S Society and Politics What Would Brezhnev Do If He Were Alive Today?...
- S Style and Beauty Choosing a Hair Straightener: Specific Criteria to Consider...
- F Family and Home How to Remove Tar Stains: Tips and Recommendations from Experts...
- F Family and Home How to Remove Fading from Clothes: Tips and Tricks...
- S Sport How to Do a Jumping Split...
- H Health and Medicine How Did Inna Lose Weight on Dom 2?...
- F Family and Home How to Properly Fold Napkins in a Napkin Holder?...
- F Food and Cooking How to Set Up Ventrilo - The Ultimate Guide...
- S Science and Technology How to Make a Homemade Smoker: The Ultimate Guide...
- A Auto and Moto Battle for the Relocation of The Cherkizovsky Market: Who Won?...
Answers on questions: Mathematics
- M Mathematics Simplify the following expression. 8x - 8y + 5z - 3x - 14y + 3z...
- M Mathematics There are (43)2 ⋅ 40 strawberries on a farm. what is the total number of strawberries on the farm...
- M Mathematics Juanita begins to factor an expression as shown. x2 + 3x – 18 = (x + )(x – ) the numbers that should be placed in the boxes, from left to right, are ....
- M Mathematics Properties of quadratic functions what quadratic function represents the graph question 1 and 2...
- M Mathematics Question 1= can kayla conclude that ∆abc and ∆edc are similar? why or why not? question 2= suppose de=175 what can kayla conclude about ab? explain. don’t forget...
- M Mathematics Solve 4x = 3/7 a: 7/7 b: 3/11 c: 3/28 d: 12/7...
- M Mathematics The relationship between the slopes of two lines that are parallel is the relationship between the slopes of two lines that are perpendicular is a line that is parallel...
- M Mathematics Me with this it is so confusing and i asked my teacher to me and she couldn t stand doing this kind of math so me as soon as possible. you to everyone who has been...
- M Mathematics Determine if the given side lengths could be used to form a unique triangle, many different triangles, or no triangles. 12 ft, 7 ft, 14 ft A. unique triangle B....
- M Mathematics Notice of the angles in the center of the pattern meet to form a circle. Let a° Represent the measure of each pink central angle and b° Represent the measure of...
Ответ:
9.3125 hours
Step-by-step explanation:
Given:
Number of components consisting in a product = 25
Standard time for work cycle = 7.45 minutes
or
standard time for work cycle =
hours
Number of units completed = 75
Now,
The number of standard hours
= Number of units completed × standard time for the work cycle
=
hours
or
The number of standard hours = 9.3125 hours
Ответ:
The best and most correct answer among the choices provided by the question is B.) 23,000
Hope this helps :)