The first unit of a product took 80 hours to complete. the firm plans to produce 10 units in the first month and 12 units in the second month. if a 75% learning curve is expected, how many hours will the firm use to work on the product during the second month? a. 960.0 hours b. 303.9 hours c. 751.0 hours d. 505.2 hours e. 447.1 hours