You have determined the critical path in a cpm analysis. you would like to determine the probability of completing the project is a desired period of time. one of the activities on the critical path has an optimistic time of 5 minutes, a most likely time of 6, and a pessimistic time of 17. what is the variance estimate of this activity?
Solved
Show answers
More tips
- F Food and Cooking What s the Best Rice for Cooking Plov?...
- F Family and Home How to Remove Fading from Clothes: Tips and Tricks...
- F Food and Cooking How to Make Polendwitsa at Home?...
- F Family and Home Parents or Environment: Who Has the Most Influence on a Child s Upbringing?...
- P Philosophy Unbelievable stories of encounters with otherworldly forces...
- L Leisure and Entertainment How to Choose the Perfect Gift for Men on February 23rd?...
- H Health and Medicine How to Treat Whooping Cough in Children?...
- H Health and Medicine Simple Ways to Lower Cholesterol in the Blood: Tips and Tricks...
- O Other How to Choose the Best Answer to Your Question on The Grand Question ?...
- L Leisure and Entertainment History of International Women s Day: When Did the Celebration of March 8th Begin?...
Answers on questions: Mathematics
- M Mathematics Rewrite 0.1 as a simplified fraction...
- M Mathematics A jet can hold 467 people per trip. How many trips would it take the airplane to transport 99,205 people? (show ur work)...
- M Mathematics Gyro bought a car priced at $7,589. He agreed to make payments of $260 per month for 36 months. How much more than the actual price will Gyro pay? $...
- G Geography The unconformity is located at the boundary between middle proterozoic rock and late cambrian and early ordovician rock. identify by name the oldest new york state...
- M Mathematics 70 points ! solve all of them...
Ответ:
The variance estimate of this activity is 4.
Step-by-step explanation:
Given information: One of the activities on the critical path has
Optimistic time = 5 minutes
Most likely time = 6 minutes
Pessimistic time = 17 minutes
The variance estimate of a activity is
where, is pessimistic time of that activity and is optimistic time of that activity.
The variance estimate of the given activity is
Therefore the variance estimate of this activity is 4.
Ответ:
Step-by-step explanation:
Breaking apart arrays is another effective strategy for students who are learning multiplication, and helps model distributive property. For example: students usually learn their twos and their fives sooner than the larger times tables, so that when faced with a problem like 6 X 7, students can instead look at the 7 as a (5+2) instead. Like this: 6 X (5+2) OR (6 X 2) + (6 X 5) = 12 + 30 = 42.