A company needs to locate three departments X, Y, and Z in the three areas I, II, and III of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load meter moved. An analyst has prepared the following flow and distance matrices: Distances meters Flows Loads per week
From / To I II III From / To X Y Z
I - 10 20 X - 0 80
II - - 10 Y 30 - 150
III - Z 100 130 -
If the company were to locate departments X, Y, and Z in areas 1, 2, and 3, respectively, what would be the total distance (in meters) loads would be moved each week?
A. 3,100
B. 3,600
C. 6,200
D. 7,200