Dog Up! Franks is looking at a new sausage system with an installed cost of $460,000. This cost will be depreciated straight-line to zero over the project's five-year life, at the end of which the sausage system can be scrapped for $55,000. The sausage system will save the firm $155,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $29,000. If the tax rate is 21 percent and the discount rate is 10 percent, what is the NPV of this project?
Solved
Show answers
More tips
- F Food and Cooking Apple Cider Vinegar: The Ultimate Health and Beauty Solution...
- C Computers and Internet Е-head: How it Simplifies Life for Users?...
- F Family and Home How to Choose the Best Diapers for Your Baby?...
- F Family and Home Parquet or laminate, which is better?...
- L Leisure and Entertainment How to Properly Wind Fishing Line onto a Reel?...
- L Leisure and Entertainment How to Make a Paper Boat in Simple Steps...
- T Travel and tourism Maldives Adventures: What is the Best Season to Visit the Luxurious Beaches?...
- H Health and Medicine Kinesiology: What is it and How Does it Work?...
- O Other How to Choose the Best Answer to Your Question on The Grand Question ?...
- L Leisure and Entertainment History of International Women s Day: When Did the Celebration of March 8th Begin?...
Answers on questions: Business
- C Chemistry Consider the following intermediate chemical equations. C(5)+ 02(g) → CO(g) CO(g)+ 02(g) - C02(0) How will oxygen appear in the final chemical equation? O2(g) as...
- M Mathematics What is the solution to this system of equations? 2/3x+y = 6 xy=2 (1, -1) (0,8) infinitely many solutions no solution PLEASE HURRY...
- H History I need help ASAP no links please i want answers...
- M Mathematics What is the value of x? 11 (9 - 2x) = -(12x + 11)...
- M Mathematics The complex number lies in the shaded area of the graph. the complex number does not lie in the shaded area. blank spot 1 1 - 3i -1 + 3i -3 + 4i blank spot 2 -4i...
Ответ:
The Net Present Value (NPV) of this project is $93,405.59.
Explanation:
Note: Find attached the excel file for the calculation of the NPV of this project.
Net present value (NPV) refers to the present value of cash inflows minus the present value of cash outflows over a specified period of time.
On its own, present value (PV) refers the value that a future sum of money or stream of cash flows has now or currently given a specified rate of return. The formula for calculating the PV is given as follows:
PV = FV / (1 + r)^n
Where,
FV = Future value
r = discount rate. This is given as 10% in this question
n = Relevant period, e.g. year
The above explanation and formula together with other stated formulae in the attached excel file is used in calculating the NPV of this project.