Maria received notification of a slight increase in the price of cement from the
project vendor, but forgot to report this fact to the project manager. they
project ended up over budget. how could this situation have been avoided?
o
a. by admitting to her manager that she needed additional .
b. by recognizing the impact of even small changes on the overall
project sucches.
o
c. by implementing budget tracking software
o
d. by taking better notes in her phone conversations.