Project teams can often identify risks by conducting any of several types of reviews. Which of the following illustrates a valuable type of risk review? a. review previous projects to verify that each current assumption is correct b. review the communication plan to determine where poor communications could cause a problem c. review the project schedule to determine if certain people are overloaded d. review sunk costs to determine project continuance