When using the Time-Cost Critical Path Method (CPM) Scheduling Model to "crash" a project, you know when you have arrived at the optimal solution when .
a) You have found the critical path
b) You have run out of crash time
c) You no longer have a linear relationship with costs
d) You have reached the minimum total cost
e) You have run out of crash costs
Solved
Show answers
More tips
- T Travel and tourism Maldives Adventures: What is the Best Season to Visit the Luxurious Beaches?...
- H Health and Medicine Kinesiology: What is it and How Does it Work?...
- O Other How to Choose the Best Answer to Your Question on The Grand Question ?...
- L Leisure and Entertainment History of International Women s Day: When Did the Celebration of March 8th Begin?...
- S Style and Beauty Intimate Haircut: The Reasons, Popularity, and Risks...
- A Art and Culture When Will Eurovision 2011 Take Place?...
- S Style and Beauty How to Choose the Perfect Hair Straightener?...
- F Family and Home Why Having Pets at Home is Good for Your Health...
- H Health and Medicine How to perform artificial respiration?...
- H Health and Medicine 10 Tips for Avoiding Vitamin Deficiency...
Answers on questions: Business
- B Business 9) Consider the budget constraint of question 8 above. However, now This results in a) a pivoting out of the budget constraint on the y-axis about the point 61/2 b) a pivoting...
- B Business Having decided which people to appoint Judith needs to communicate with the successful candidates. Recommend one suitable form of communication Judith could use and explain...
- B Business What are the two main components of FICA? *...
- B Business The expenditure approach to calculating a nation’s GDP is to add:a. the value of final products minus the cost of intermediate goods used in the production process.b. wages...
- B Business The criteria for an effective team includes all of the following EXCEPT:a. team viability. b. member satisfaction. c. projected synergy. d. task performance. e. All of these...
- B Business Aquafina operates in the bottled water industry. The companies that offer identical or similar products and go after the same customers that Aquafina does are Dasani and Zephyrhills....
- B Business The employees of Antrobe, a leading daily newspaper, believe that their managers encourage them to voice their ideas and opinions. They also believe that they are given challenging...
- B Business After finishing college, Nathan joined his uncle s company in Miami, FL, a company that buys bauxite, copper, and other minerals from the country of Chile, and brings them...
- B Business I m doing a speech about why people give up and why they shouldnt give up what should my attention getter and my main points be?...
- B Business Qué aspectos consideras relevantes dentro de una mega tendencia? Ayuda porfavorr...
Ответ:
a) You have found the critical path
Explanation:
The Time Cost Critical Path Method(CPM) in project management works by adding up/calculating duration of all tasks/activities in the project in order to find the longest time possible to complete the project. It is a method to estimate project duration using a flow chart that shows a network of tasks and estimated duration(start and finish times). The critical path is reached when project time is at the maximum/longest time of completion.