When using the Time-Cost Critical Path Method (CPM) Scheduling Model to "crash" a project, you know when you have arrived at the optimal solution when . a) You have found the critical path
b) You have run out of crash time
c) You no longer have a linear relationship with costs
d) You have reached the minimum total cost
e) You have run out of crash costs